The Surbiton to Kingston scheme is partially complete.

Works on Avenue Elmers and Palace Road were completed in February 2017 and a new one-way cycle lane on St Mark's Hill was opened in April 2017.

New signage was installed at the end of September 2017 for the permanent traffic restriction on Surbiton Crescent. The second stage will be to implement the full permanent layout, removing the temporary blocks and installing permanent traffic islands and other features. We currently plan to complete these works in November 2017. The traffic cameras will remain in place but the Council has switched to intermittent enforcement and will continue to monitor traffic flows in the area. 

Construction works in The Crescent and Claremont Road are planned to begin in November 2017. This will involve:

  • temporary footway closures
  • temporary parking bay suspensions
  • re-aligning the kerb
  • re-laying the footway

The remaining works will take place in early 2018, including the installation of the cycle lane in Claremont Road and new controlled crossings at the Maple Rd/Claremont Rd junction.
 