Traffic updates

Delays possible to your journey time, particularly at peak times.

Last updated 4th October 2024.

Go Cycle 

The Go Cycle project has started. This will have a large impact on Ewell Road (A240) and the surrounding area while it is in progress.

This is a very long project spanning multiple permits and roads. Permits will advise of longer durations and more disruptive traffic management than will typically be in place.

As the works proceed we will update permits for this project accordingly. Use Google Maps or One.Network to keep informed about real time traffic flows.

Surbiton Hill Road, Surbiton

  • 24 hour road closure at the junction with Beaufort Road - side of Hollyfield School.
  • 30 August to 2 November 2024.
  • Works by UK Power Networks.

Cambridge Grove Road, Kingston

  • 24 hour Road closure of entire cul-de-sac.
  • 13 June 30 November 2024.
  • Works by RBK.
  • Footway closed. An alternative route for pedestrians will be provided.

Cromwell Road, Kingston

  • 24 hour lane closure outside the bus station.
  • 25 June 2024 to 28 February 2025.
  • Works by Thames Water.
  • Footway closed. A pedestrian walkway will be provided.

Acre Road, Kingston

  • 24 hour road closure from 74 to the junction with Richmond Road.
  • 5 August to 29 November 2024.
  • Works by SGN.
  • Footway closed. An alternative route for pedestrians will be provided.

St James Road, Kingston

  • 24 hour road closure. 
  • 2 September to 4 October 2024.
  • Works by RBK.
  • Footway closed. An alternative route for pedestrians will be provided.

Cox Lane, Chessington

  • 24 hour two - way signals outside Buildbase.
  • 23 September to 4 October 2024.
  • Works by RBK.
  • Footway closed. An alternative route for pedestrians will be provided.

Cox Lane, Chessington

  • 24 hour multi-way signals outside Alliance Healthcare to junction of Mount Road on Cox Lane.
  • 7 to 15 October 2024.
  • Works by City of London Telecoms.
  • Footway closed. A pedestrian walkway will be provided.

Coterill Road, Tolworth

  • 24 hour road closure outside 11 - 25.
  • 7 to 18 October 2024.
  • Works by RBK
  • Footway closed. A pedestrian walkway will be provided.

Oak Hill Grove, Surbiton

  • 24 hour road closure outside number 9.
  • 7 to 10 October 2024.
  • Works by Thames Water.
  • Footway closed. An alternative route for pedestrians will be provided.

Cromwell Road, Kingston

  • 24 hour lane closure outside Cromwell Road bus stop.
  • 7 to 25 October 2024.
  • Works by TFL.
  • Footway closed. An alternative route for pedestrians will be provided.

Horsefair, Kingston

  • Road closure 22:00 - 04:00 at the entrance to the John Lewis tunnel eastbound lane.
  • 21 to 22 October 2024.
  • Works by RBK
  • Footway closed. An alternative route for pedestrians will be provided.

Ewell Road, Surbiton (Go Cycle works)

  • Road closures and two-way traffic lights from 132 to 166.
  • The project will run until March 2025.
  • Works by RBK.
  • Footway closed. An alternative route for pedestrians will be provided.

Langley Road, Surbiton (Go Cycle works)

  • Road closure from Ewell Road to 158.
  • The project will run until March 2025.
  • Works by RBK.
  • Footway closed. An alternative route for pedestrians will be provided.

Oak Hill Crescent, Surbiton (Go Cycle works)

  • Road closure at the junction with Ewell Road.
  • The project will run until March 2025.
  • Works by RBK.
  • Footway closed. An alternative route for pedestrians will be provided.

South Bank, Surbiton (Go Cycle works)

  • Road closure at the junction with Ewell Road.
  • The project will run until March 2025.
  • Works by RBK.
  • Footway closed. An alternative route for pedestrians will be provided.

South Place, Surbiton (Go Cycle works)

  • Road closure at the junction with Ewell Road.
  • The project will run until March 2025.
  • Works by RBK.
  • Footway closed. An alternative route for pedestrians will be provided.

South Terrace, Surbiton (Go Cycle works)

  • Road closure at both junctions with Ewell Road.
  • The project will run until March 2025.
  • Works by RBK.
  • Footway closed. An alternative route for pedestrians will be provided.

Last Modified: 04/10/2024 10:33:21