This Guidance has been prepared to assist developers and contractors to undertake construction and demolition works in a manner which will minimise the disturbance to neighbours in the vicinity of their site. Adherence should ensure that disturbances from noise, vibration, dust and smoke caused by all site activities are controlled to an acceptable level.
Our objective is that all development works proceed with minimum disruption to the developer and public alike. However we have a duty to enforce the legislation listed below where guidance is not being followed or nuisance is being caused and will not hesitate to implement formal action to protect public amenity when appropriate.
It is therefore in your interest to be aware of your statutory responsibilities in regard to environmental protection.
The Control of Pollution Act 1974 gives Local Authorities the power to serve a Notice Imposing Requirements upon contractors and developers which sets out how works should be carried out in order to minimise noise arising from a number of defined activities which include, works of demolition and construction and repair and maintenance of buildings. Although there is provision to specify maximum noise levels permitted from the site, control is usually exercised by restricting the hours of noisy operations. This applies to any noisy activity and ensures that noise from the site which is audible beyond the site boundary, or at any such place agreed by us, shall only be carried out between the following hours:
MONDAYS to FRIDAYS 8am to 6pm
SATURDAYS 8am to 1pm
SUNDAYS AND BANK HOLIDAYS NO NOISY WORK
In practical terms, as long as no planning conditions apply restricting actual working hours, we would not object to the presence of workers on site outside these hours provided they are engaged only in non-noisy operations. For this reason, strict control must be exercised at all times and a person in authority must be nominated to ensure that the restrictions are not breached.
The requirements of a Notice will also apply to deliveries of plant or materials to, and collections from, the site. It is recognised that such activities often take place prior to 8am. However, in cases where the site is adjacent to residential properties this practice would not be acceptable. In circumstances where noise from out-of-hours deliveries leads to complaints, it would be expected that contractors would actively prevent access to the site outside of the permitted hours. Should this cause obstructions to the highway, the vehicle should be brought onto site and the engine turned off. No loading/unloading should take place until 8am, unless it is possible to load/unload without causing noise audible beyond the site boundary. Where persistent problems of delivery vehicles arriving too early exist it is expected that written instructions are given to offending companies of the restrictions that exist on the site.
In cases where noisy work is likely to arise outside the permitted hours, we will require notice, in writing, at least 72 hours in advance. The application should detail the nature and reason for the works and the proposed timetable. Each application will be considered on its own merits and a decision will usually be made within 24 hours.
It is a requirement that plant and machinery used on the site shall be properly silenced and that the best practicable means to reduce noise to a minimum shall be employed at all times. In particularly noise sensitive areas, or if plant needs to operate at night, more stringent requirements may be imposed. The contractor should demonstrate best practice by adopting the recommendations of:
British Standard 5228:2009 – Code of practice for noise and vibration control on construction and open sites.
BRE Pollution Control Guide - Controlling particles, vapours and noise pollution from construction sites
The Clean Air Act 1993, subject to certain specifc exemptions and control provisions, prohibits the emission of "dark" smoke from any industrial or trade premises. In addition the Environmental Protection Act 1990 empowers a Local Authority to take action when smoke of any type is causing or likely to cause a Statutory Nuisance to the inhabitants of a neighbourhood.
We view the indiscriminate burning of construction or demolition waste as a serious environmental issue and will not hesitate to take formal action where a contractor fails to observe good practice. Unless the Planning Department have attached conditions to the planning consent prohibited the burning of waste materials on site, burning should only take place in exceptional circumstances when all other disposal options have been considered. The contractor should demonstrate best practice by adopting the recommendations of the BRE Pollution Control Guide - Controlling particles, vapours and noise pollution from construction sites.
In cases where we have received complaints, or we have reason to believe that burning is to take place and nuisance is likely to occur, we will serve an Abatement Notice upon the contractor prohibiting nuisance and specifying steps to be taken. These are as follows:
We give high importance to the protection of air quality and have designated the whole Borough as an Air Quality Management Area under the Environment Act 1995. Our Air Quality Action Plan attaches particular emphasis to reducing the emission of fine particles into the atmosphere and local emission sources from demolition and construction works have been targeted for priority action.
It is an offence under the Environmental Protection Act 1990 to cause nuisance to the inhabitants of the neighbourhood by generating dust. In cases where we have received complaints, or we have reason to believe that dust may be generated and nuisance is likely to occur, an Abatement Notice may be served upon the contractor.
When undertaking demolition or construction works during periods of dry and/or windy weather, dust problems often prevail, particularly on sites bordered by residential properties. The Act requires that Best Practicable Means must be taken to prevent dust causing a nuisance and it is the duty of the contractor to demonstrate to us that all reasonable remedial action has been implemented. The following steps should be considered:
The contractor should demonstrate best practice by adopting the recommendations of the BRE Pollution Control Guide - Controlling particles, vapours and noise pollution from construction sites and Best Practice Guidance: The Control of dust and emissions from construction and demolition published by the GLA and London Councils
Under the provisions of the Control of Pollution Act 1974, it is a general requirement that contractors apply Best Practicable Means in order to minimise noise and vibration arising from piling operations. The contractor should demonstrate best practice by adopting the recommendations of:
British Standard 5228:2009 – Code of practice for noise and vibration control on construction and open sites.
BS6472:1992 – Guide to evaluation of human exposure to vibration in buildings (1Hz to 80Hz)
BS7385: Part 2, 1993 – Evaluation and measurement for vibrations in buildings
BRE Digest 353 (deals specifically with damage to structures from ground borne vibration).
The contractor should be fully conversant with these documents when selecting a piling method. The decision regarding the piling method to be used will normally be governed by such criteria as loads to be carried, strata to be penetrated and economics of the system. However noise and vibration should also be a significant factor and contractors should seek to select a method that is not only suitable for their needs but will cause the least amount of noise and vibration. The contractor should be able to demonstrate to us that not only the chosen method is the most suitable, but that Best Practicable Means are being taken.
Piling operations are a common cause of complaint, particularly where vibrations are felt. If, after suitable investigation and experimentation with alternative piling methods it is agreed that the contractor is taking the Best Practicable Means to minimise noise and vibration, it is expected that the contractor will reach an agreement with local residents/occupiers of commercial properties about the times when piling occurs, as it would not be reasonable for disturbance to occur throughout the entire working day. Where there are concerns about the potential damage that may be caused by vibration to properties it is expected that the contractor will liaise directly with the complainants and, if necessary, employ an expert to measure the vibration generated and give appropriate advice to all parties. In certain circumstances it may be prudent to have a building surveyor inspect residential properties prior to commencement of piling.
It will generally not be acceptable for the contractor to select a method which utilises the unrestricted use of percussive or vibrational energy to drive or extract piles and where suitable conditions exist, piling using these methods should be avoided. It is recognised that despite the correct advice being sought at the planning and design stage, problems of noise and vibration are sometimes encountered on site. At such a time it is incumbent upon the contractor to modify the selected piling process or to select a different method or a combination of methods to remedy the problem. It is expected that piling would cease until such time as an acceptable method as been agreed upon.
Failure to observe Best Practicable Means and allowing the occurrence of excessive noise or vibration, may result in us taking action to restrict or prohibit the works.
The Environmental Permitting (England and Wales) Regulations 2010 require that most activities managing or treating waste should have a permit. However, there are some exceptions. These are called exemptions. Exemptions are waste operations that do not need a permit but do need to be registered.
Most exempt waste operations are registered by the Environment Agency, however local authorities including the Royal Borough of Kingston upon Thames register some waste treatments including Mobile Crushing Units known as T7 activities:
T7 activities are the crushing, grinding or other size reduction of waste bricks, tiles or concrete typically using small-scale/micro crushers and can include some mobile plant. If you operate mobile plant and your principal place of business is within the Royal Borough of Kingston upon Thames you may obtain an exemption from us, otherwise you should contact your home local authority. If your principal place of business is outside of the United Kingdom then we can still register your exemption if the activity is to be carried out within our borough.
To qualify as a T7 exempt waste operation the activity must also meet the following criteria:
If you carry out the above activities but cannot meet the specific criteria then it is likely that a full permit under the regulations is required.
If your principal place of business is within the Royal Borough of Kingston upon Thames and you need to apply for a permit or register an exempt waste operation please contact the Environmental Health Service for an application form.
y them, in advance, of any events that may be different to normal operations·
Plan work to minimise nuisance. Take steps to control noise, dust and smoke arising from operations on site
Keep roads leading off the site clean and tidy
Implement a formal complaints procedure
Ask site staff not to park in residential roads and implement effective access and traffic management measures for all site vehicles.
The contractor should consult with the Health and Safety Executive when removing asbestos materials.
When carrying out development work on land with a historic commercial use it is possible that contractors may expose hot spots of ground contamination evident by colour, residue or odour. The contractor should contact us and ensure that contaminated soil is appropriately dealt with according to current guidance and health and safety of workers is maintained.
In accordance with the GLA Supplementary Planning Guidance on Sustainable Design and Construction 2005 it is recommended that developers produce a waste or recycling plan to ensure that waste materials are identified with the aim of reducing waste as much as possible through reuse or recycling. Best practice procedures for waste plans are also available from the Environment Agency.
The Health and Safety Executive is the enforcing authority for the above legislation on demolition and construction sites and will be informed of any complaints received regarding possible hazards to the public and/or workforce on site. Your notice is drawn to the requirements of the Act and to the interest this Council has in protecting the public. For further information or advice contact the Health and Safety Executive (Construction Group), Rose Court, 2 Southwark Bridge, London SE1 4LW. Telephone 020 7556 2100.