      New Secondary School Consultation, January - February 2010

 

New Secondary School Consultation, January - February 2010

Comments received during the new secondary school consultation - 1 January to 26 February 2010

Below we have also attached documents outlining all comments received during the consultation period. We have included responses  provided by the Canbury Area Residents Association (CARA) Survey, the London Borough of Richmond upon Thames and Grey Court School.

Public Meeting - 9 February 2010

A public consultation meeting was held on Tuesday 9 February 2010 at Fern Hill Primary School.  A copy of the presentation made at the meeting and notes of the comments and questions made can be obtained below.  

Planning and Design

At the Public Meeting a change in the arrangements for the planning and design of the new school was outlined. The attached document explains why the Local Authority will be undertaking a planning brief approach rather than submitting a planning application during the period April – August 2010 as outlined in the original table.

The amended timetable will now involve: -

  • June to Mid July 2010 – consultation on a Planning and Development Brief for the North Kingston Centre site
  • September 2010 – anticipated that planning security provided to Partnership for Schools
  • Early 2011 – pre-application consultation prior to the submission of a planning application

Get help accessing files or request files in an alternative format.

 
Search the Site

The Royal Borough of Kingston upon Thames, Guildhall, High Street, Kingston upon Thames, KT1 1EU

Contact Us | SMS: 07797 806 521
Emergency Out of Hours: 020 8547 5800